Coaches Corner

LPC Project Coaches share their views on creating lean design and construction projects and lean enterprises.
Category >> LPS® Best Practices
Jun 19
2009

Are you running junk miles?

Posted by John Draper in LPS , Lean Construction , Last Planner System , last planner

John Draper

There is a training principle adhered to by most distance runners that states that each workout needs to have a purpose or objective.  Are you going to work on endurance, speed, hills, etc?  Just going out and running without a purpose is known as running "junk" miles, which does nothing to make you a better runner and could lead to injury.

So, on your LPS project, are you "running junk miles"?  Are you going through the motions of the LPS without really having a purpose?  After you are proficient with the mechanics of the LPS, you should focus on an improvement objective each week.  According to Geoff Colvin in his book Talent Is Overrated, high performance is a result of "deliberate practice" and not a result of just plain hard work or innate talent.  The special kind of hard work that Colvin describes is focused on an objective and is repeated with discipline until you get it right or obtain the improvement that you were seeking.  It is not fun and usually "hurts."

If you really want to improve, stop running "junk miles" and institute a discipline of "deliberate practice" on your project.

Jun 05
2009

Is Your Project Under Control?

Posted by John Draper in Untagged 

John Draper
How do you go about answering this question?  First you may ask, "What do you mean by ‘under control'?"  In my mind there are two dimensions to project control, financial and operational.  Although both of these are highly dependent on and interrelated to each other I am going to just talk about operational control in this blog.  In my view, a project is in operational control when the work that is being done is the work that should be getting done.   Okay then, what work should be getting done?  The milestone plan or high level master schedule establishes what should be happening and when on the project in order to deliver it to the client as promised.

Here is a simple way to assess your project.  Get a copy of the latest work plan, look-ahead plan, schedule or whatever you use on your project to schedule work crews.  Does the work plan support what should be done on the project for the time period in question?  Go out onto the project and observe.  On what tasks does the work plan say that crews should be working?  Are they?  Are they working on tasks which don't appear on the work plan or should be happening in the future or should have happened in the past?

I think you will be surprised to find that your project isn't as under control as you might have previously thought.  So what can we do to bring it under control?  The Last Planner® System, which was developed precisely because of this observation, is a methodology for bringing and keeping a project under operational control.

Jun 01
2009

Think Small Batch Size!

Posted by John Draper in Lean Construction , Last Planner System , best practice , batch size

John Draper

One of the precepts of lean manufacturing is the reduction of batch size as a means to control overproduction.   Since the concept of "overproduction" on a construction project is more difficult to grasp we tend not to pay a lot of attention to batch sizes.  This neglect can result in less than efficient production and even worse.  By batch size, I am referring to the amount of "work-in-place" that is released to the next trade. 

Here is an example from a multi-unit residential project to illustrate the point.  This project consisted of several multi-story buildings.  Each floor was framed-out with metal studs and gypsum wallboard.  As typical, the metal framer went through each floor erecting the metal studs, with the plumber and electrician following a floor or so behind with their rough installation.  As part of his installation, the plumber installed prefabricated shower units in pre-framed alcoves.  However, when he installed the shower nozzle piping, he had to do so off-center in the shower because a double wall stud assembly had been constructed dead-center behind the shower enclosure.  Since, no one was paying attention to batch sizing and the framer was ahead of the shower installation crews by several floors when this issue was discovered, instead of one or two off-centered shower heads, now there were several hundred.  If the framer had not "overproduced" framed walls and gotten so far ahead of the plumber, only one or two framed walls would have had to be changed for proper installation of the shower head and the stud layout could have been adjusted on all future walls.

The reliable workflow that results from the disciplined use of the Last Planner® System allows the project team to closely coordinate their work on the project which in turn provides the opportunity for the reduction of batch sizes.  On such a project, there would be no advantage and only disadvantages for having the framer more than a couple of days ahead of the plumber.

Apr 24
2009

How do you make work ready?

Posted by John Draper in Lean Construction , Last Planner System

John Draper

I have written before about the importance of make-ready planning in creating and maintaining reliable workflow on a project and establishing the discipline of setting aside a block of time each week to actually do this planning.  But how do you actually go about making work ready?  Do you follow a detailed procedure or do you just "think" about the upcoming work in your head.

Just as a pilot who has landed a plane 1000 times will use one on the 1001st and each succeeding landing, proficient last planners will not leave make-ready planning to chance but will use a set procedure and checklist to guide them in this critical effort.  What sorts of things should the last planner be doing in order to make work ready?  First, although make-ready planning is largely a "mental activity" one should put pencil to paper in a manner akin to how we use these items in solving complex math problems.  Next, develop and follow a set procedure for doing make-ready planning.  Here is a starting point:

Week 6

Mar 26
2009

Make it a habit to routinely analyze your constraint logs.

Posted by John Draper in Untagged 

John Draper
 Make-ready planning is critical to creating and maintaining reliable workflow on the project.  The constraint log(s) is integral in managing the make-ready planning process, which consists of two specific planning activities:  (1) identifying constraints and (2) obtaining commitments from individuals to remove the constraints.

Without a periodic assessment and adjustments based on the assessment, the log can quickly become an ineffective listing of all known "hot" items.  It takes discipline on the part of the team to self-police the log to continuously ensure that it remains an effective tool in the make-ready planning process.  Consider the following points and questions to gauge the level of effectiveness of your log:

  • Have you established a separate log for each phase plan?
  • Is each entry in the log tied to an activity or activities on the phase plan?
  • Has the "Date Need Resolved" been established for each constraint?
  • Has an individual made a committment to remove the constraint and if so is there a "Date Promised"?
  • If "Date Promised" is after "Date Need Resolved," what have you changed in the plan to accommodate the discrepancy?
  • If a constraint hasn't been relieved by "Date Promised," what follow-up action have you taken to get a new commitment and what re-planning have you done to adjust to this new reality?
  • Comparing the "Date Identified" with the "Date Need Resolved" will give an indication of how well the make-ready process is working. Ideally, you want to identify constraints during the first week that the activity shows up on the look-ahead plan. This means that the "Date Identified" should be upwards of 5 to 6 weeks ahead of the "Date Need Resolved." If these two dates are close, it means that constraints are being identified just prior to when they need to be relieved, leaving little time to do so.
Mar 16
2009

Keep your phase plans current.

Posted by John Draper in Untagged 

John Draper

Your phase plan(s) should represent the current best vision of how your project will unfold.  Otherwise, they will soon become irrelevant for managing the project and will be ignored by the project team.  In order to efficiently make work ready to be accomplished, one must have a good idea of what work will need to be done at specific times in the future.  Without a phase plan that is current, each project member will form their own opinion as to what is planned to happen on the project over the look ahead period (normally 6 weeks).  These mental plans will only be similar to each other and reality by chance.  Consequently, work will be made ready that is not within the look ahead window and more importantly, work that is within the window will not be made ready exposing the project to weekly work plan failures.

Now that we have established the importance of keeping phase plans current, the question then becomes "How often should we update the phase plans?"  There are two aspects to this: tracking progress and modifying the plan.  As you might guess there is no simple or correct answer.  Progress should be updated at least once per week.  On highly detailed and fast moving project plans, perhaps the plan will need updating every day and on plant shutdowns maybe every hour.  If the project is evolving as detailed in the phase plan then we have finished our updating for this cycle.  However, if we are not where we planned to be on the project, the team must assess the situation and take some type of action otherwise the attainment of the phase milestone will be put in jeopardy.   Despite the strong reluctance to "change" the plan no matter the source of this anxiety, we have to "bite the bullet" and modify the plan to reflect current reality.  This could be as simple as putting on a second shift in specific trades or as drastic as developing a new phase plan through the pull planning process.  The important thing to remember is that the team must be continuously proactive to ensure that the phase plan reflects the collective best vision of the future.

Mar 03
2009

The Discipline of Making Work Ready

Posted by John Draper in Untagged 

John Draper

Get into the discipline of setting aside a block of time each week to "make work ready."  One of the most important facets of the Last Planner System that sets it apart from the traditional  approach to project management is the practice of explicitly making work ready to be accomplished when scheduled.  Unless work is "made ready" it is a crap shoot whether or not it will be able to be completed as originally scheduled.  Teams that are routinely successful in creating and maintaining reliable work flow have established the disciplined practice of setting aside a couple of hours at the same time each week to make work ready.  Just as working out each day at the same time helps to discipline ourselves into following a set routine, sitting down in the office each week at the same time to study the upcoming work and reviewing constraints is very effective in developing the necessary discipline to make this a habit.

Feb 25
2009

Last Planner Best Practice Series

Posted by Hal Macomber in pull planning , last planner , daily coordination , best practice

Hal Macomber
John Draper, P.E., Sr. Project Coach, will be writing a regular series on the best practices that LPC observes on client projects.  His posts will be short, action-oriented, and ready for your adoption.  Let John know when you put one of the best practices into use.  And, don't hesitate to share your best practices with John.

Coaches Corner

  • Lean Psychology

    I really enjoyed Karen Martin's free webinar on Lean Psychology today. 


    http://www.ksmartin.com/webinars/


    Her examples and instruction are very proactive; I appreciate that. Following her tips we change agents are sure to avoid pitfalls. Much of the discussion...

  • What would I cover at a Lunch and Learn

    Hello,


    I am doing a 2 minute survey on surveymonkey.com to understand better what your questions are. I've been making offers to come to your office for an hour to present and discuss Lean. With your...

  • 4 Elements of Change

    Construction, like healthcare, is learning from another industry. I was just watching David Fillingham, Chief Executive, Royal Bolton Hospital NHS Trust give his speech on Managing the Lean Hospital: what it takes to engage the whole...

  • A3 Problem Solving for Healthcare/Construction???

    It is challenging to learn from other industries. Construction is not the first industry to adopt lean; there are great examples in the healthcare industry. I just read A3 Problem Solving for Healthcare: A Practical...

  • Chief Social Architect for Projects

    Projects are made up with people thrown together. Establishing the role of a relationship designer in a project based company has many practical purposes. Let's call that person the Social Architect (SA). The Project Managment...